SPIKE: AISDLC-95 model-routing implementation plan
Feature: AISDLC-95Refinement epic: AISDLC-287Date: 2026-10-12 Status: Proposed for reporter review; not approved for implementation
Purpose
This document consolidates the research from the five AISDLC-287 spikes into an implementation sequence that can be reviewed before AISDLC-95 is broken down into delivery epics and stories.
It is not an accepted Fullsend architecture. The AISDLC-95 reporter must approve the product direction and resolve or explicitly defer the decision gates below before the delivery breakdown is created. Any learned or LLM-based production routing decision also requires a new Fullsend ADR.
Jira spike inputs
The implementation sequence is derived from the issue-specific research, prototypes, and implementation plans:
- AISDLC-288 acceptance criteria: research, prototype and implementation plan
- AISDLC-289 external gateway: research, prototype and implementation plan
- AISDLC-290 offline policy authoring: research, prototype and implementation plan
- AISDLC-291 pre-run advisor: research, prototype and implementation plan
- AISDLC-292 related-work boundaries: research, prototype and implementation plan
Accepted architecture baseline
The implementation must compose with these accepted decisions:
- ADR 0112 defines deterministic per-task
modelandeffortselection through harness overlays, including source precedence, resolution traces and typed fallback. It explicitly defers LLM-based routing to AISDLC-95 and requires another ADR. - ADR 0137 defines an inference gateway as a credential route of its own. Once selected, gateway failures cannot escape to a direct-provider route.
- ADR 0138 adds an explicit
api-keycredential mode to the gateway route. It does not create fallback or precedence between OIDC and API-key modes.
ADR 0112 was accepted but its complete model/effort overlay behavior was not implemented on the research baseline. That deterministic foundation should be completed before automatic routing enforcement.
Proposed implementation shape
The research supports a layered approach. These are recommendations for reporter and architecture approval, not recorded decisions.
- Offline policy authoring is the governance layer. Repeated evaluation and production evidence may propose a versioned routing policy. A proposal cannot activate itself. Human approval, signed artifacts, independent activation, promotion gates and exact rollback preserve deterministic production behavior.
- A pre-run advisor is the task-aware candidate. A host-side advisor may recommend a concrete model and effort or abstain. Fullsend policy decides whether the recommendation is allowed. Shadow mode always executes the existing static selection. Enforcement requires a new ADR and an accepted application point.
- The external gateway begins as serving and enforcement. The existing gateway route serves an approved concrete
gateway/<model>choice. It is not presumed to be the automatic selector. A gateway selector would need a separately approved control contract, route-isolated failure behavior, authenticated repository-bound calls, conformance evidence and a new ADR. - Pinned and deterministic overlay modes remain first-class. Pinned mode is the safe baseline and rollback. Reviewed evidence can also produce a deterministic overlay policy without introducing a live classifier.
Invariants
Every later epic and story must preserve these constraints:
- Automatic routing is opt-in. Pinned routing remains supported and is the rollback target.
- Author-controlled input cannot establish or relax the security floor, provider policy, credential route or egress policy.
- Shadow routing cannot change the model or effort that actually executes.
- Requested alias, advisor recommendation, accepted selection, runtime request and actual served model remain separate recorded identities.
- Missing cost, usage, served-model or quality evidence remains unknown. It is never converted to zero or success.
- Gateway response metadata, gateway telemetry and gateway exports share one gateway trust domain. Self-consistency is not independent proof of the upstream provider or model.
- Once the gateway route owns a selection or control call, failures stay on the same configured gateway block and ADR 0138 authentication mode. The only permitted recovery is a preapproved concrete gateway fallback or fail closed.
- OIDC and opaque API-key validation remain mode-specific. Upstream API-key revocation and optional contract expiry are distinct from the run-scoped OpenShell provider lifetime.
- A production-adjacent gateway pilot that may outlive the observed OIDC token lifetime requires per-runtime live proof of rotation, settle, re-seed, credential-file re-read and fail-closed behavior.
- Historical evidence cannot directly mutate live policy. Cost is evaluated only after evidence-integrity, security, deterministic, quality, completion and operational gates pass.
Reporter decision gates
The reporter should approve an option or explicitly defer each item before the delivery epic/story breakdown is created.
| ID | Decision required | Recommended starting point |
|---|---|---|
| D1 | Which surfaces may v1 route? | Top-level agent model and effort; leave runtime and persona/subagent routing out until separately assigned. |
| D2 | Which candidate placements proceed? | Offline governance plus a pre-run advisor experiment; gateway serves concrete choices and is not initially the selector. |
| D3 | May a classifier participate? | Yes in offline evaluation and shadow; enforcement only after evidence and a new ADR. |
| D4 | May a security-relevant stage be downgraded? | Keep it pinned or escalation-only unless a later approved policy defines trusted downgrade evidence. |
| D5 | What does AISDLC-5 block? | Block policy promotion and production enforcement, not deterministic foundation work or offline experimentation. |
| D6 | What is the first golden-path pilot? | Select one named workflow after confirming its evaluation data and ownership; treat AISDLC-116/AISDLC-24 as a candidate, not an encoded blocker. |
| D7 | What budget does AISDLC-95 own? | Routing-time per-invocation or per-stage policy; consume AISDLC-345 cost evidence and leave cumulative enforcement to AISDLC-282. |
| D8 | What satisfies configuration without code changes? | A reviewed custom harness/configuration is sufficient for v1 if operators can version, inspect and roll it back. |
| D9 | What happens after a quality failure? | Define one bounded escalation attempt with an explicit new attempt identity; do not imply transparent continuation. |
| D10 | May historical evidence change live policy? | Reviewed, versioned offline updates only for v1. |
| D11 | What may be claimed from AISDLC-15? | Hummingbird interest and an exploratory integration recommendation only; gateway availability and selector capability require separate proof. |
| D12 | Which signals may v1 use? | Close and version a minimal signal set before implementation; record provenance and author-control classification for every signal. |
Proposed delivery sequence
Phase 0: approval and architecture closure
- Obtain reporter approval for D1-D12.
- Record explicitly deferred decisions and owners.
- Confirm whether the approved direction needs one new ADR or separate ADRs for the advisor application point and gateway-selector control plane.
- Re-read current Jira and repository state before creating delivery work.
Exit gate: the reporter approves the planning basis and every unresolved item has a decision, owner or explicit deferral.
Phase 1: deterministic routing foundation
- Finish ADR 0112 model/effort overlay implementation.
- Preserve ADR 0091 source precedence.
- Emit the overlay-resolution trace and fallback reason.
- Implement and test the typed unserved-model retry without overlays.
- Keep pinned behavior as the comparison baseline and rollback.
Exit gate: deterministic conformance, fallback and resolution-trace tests pass.
Phase 2: routing evidence contract
- Define stable decision, invocation, attempt, work-item and stage identities.
- Integrate authoritative cost evidence from AISDLC-345.
- Record recommendation, accepted selection, requested runtime model, actual served identity, fallback/escalation, latency, cost and outcome.
- Carry attester, source, trust domain, freshness and assurance on identity evidence.
- Define queryable evidence without duplicating AISDLC-282 cumulative spend enforcement.
Exit gate: a representative multi-attempt run can be reconstructed without coercing missing evidence into a successful value.
Phase 3: offline policy authoring and evaluation
- Create an immutable evaluation ledger with unsuccessful experiments retained.
- Define the pinned baseline, versioned golden path and repeated-trial method.
- Evaluate deterministic policies and advisor candidates against the same fixtures.
- Apply evidence-integrity, security, deterministic, quality, completion and operational gates before cost.
- Require human approval, signed policy artifacts, independent activation and exact rollback.
Exit gate: AISDLC-5 promotion requirements selected in D5 pass for the chosen pilot, and the candidate is non-inferior within the approved tolerance.
Phase 4: pre-run advisor shadow
- Refactor static resolution into one atomic host-side planning boundary before model-dependent credential, route and sandbox planning.
- Implement a strict versioned advisor input/output and abstention contract.
- Apply deterministic provider, model, security and capability policy after every recommendation.
- Run offline first. Permit live shadow only after destination, privacy, credential and egress review.
- Always execute the static choice in shadow mode.
Exit gate: shadow evidence is attributable, policy violations fail closed, abstention is deterministic, and no shadow decision changes execution.
Phase 5: controlled advisor enforcement
- Write and accept the required Fullsend ADR.
- Implement the approved application point and precedence matrix.
- Start one opt-in production-adjacent pilot.
- Monitor quality, completion, escalation, latency, cost, drift and evidence health with predefined stop rules.
- Exercise rollback to pinned mode.
Exit gate: the pilot passes its approved quality and operational thresholds and demonstrates rollback.
Phase 6: optional gateway-selector experiment
This phase is not required for the first advisor implementation.
- Define a provider-neutral authenticated selector control contract.
- Keep control and inference calls on the configured gateway route.
- Validate exact repository authorization and mode-specific credentials.
- Test malformed, denied, stale, conflicting, timed-out and unreachable responses; every case uses a trusted concrete gateway fallback or fails closed.
- Prove actual-served identity at the assurance required for each claim.
- Complete per-runtime long-run OIDC rotation proof before any pilot that may outlive the observed token lifetime.
Exit gate: a new ADR is accepted and the route, credential, conformance, identity-evidence and operational-proof gates pass.
Verification expectations
- Unit tests for policy ordering, abstention, fallback, precedence and mode-specific authentication.
- Behavior tests for pinned, deterministic-overlay, shadow and enforced modes.
- Adversarial tests for author-shaped inputs, forged gateway evidence, repository mismatch, credential leakage, route escape, malformed control responses and missing evidence.
- Repeated golden-path evaluation with uncertainty, exact configuration and artifact provenance.
- Go production changes meet the repository patch-coverage gate.
- User-facing configuration, CLI and operational behavior updates include the required documentation changes.
Proposed Jira progression
No Jira mutation is authorized by this document. After reporter approval:
- Record the approved D1-D12 decisions on AISDLC-95.
- Attach or link the final research findings to AISDLC-287 and each child spike, preserving the distinction between findings and accepted decisions.
- Transition the five research spikes and AISDLC-287 only after their findings and remaining owners are recorded.
- Create delivery epics from the approved phases, then create stories with testable acceptance criteria, dependencies and ADR gates.
- Link AISDLC-345 as the cost-evidence source and AISDLC-282 as cumulative enforcement ownership. Keep AISDLC-5's exact blocking milestone explicit.
- Re-read every affected issue immediately before mutation and show the exact proposed Jira changes for human approval.